Watershed Board Approves Change Orders Following Permit Delay, Other Shifts

The Shell Rock River Watershed District board approved change orders totaling over $50,000 Tuesday as it continues work with Veit & Co. Inc. for construction on the second and third confined disposal facility cells for the Fountain Lake dredging project.

The largest and most recent change order — and a bulk of that cost — asked the district for $40,000 due to a delay in the wetland permit and nonutilization of equipment.

“With the effects of the weather, you know we had such a wet summer and fall, delayed the tile work that we needed to do,” said Shell Rock River Watershed District Board Administrator Andy Henschel. “… Due to those delays, it delayed the permit.”