Watershed District Preparing for Dredging Phase Two

Problems caused by soil types at the site for confined disposal facilities two and three meant the Shell Rock River Watershed District board passed a change order Thursday that more than tripled the bid price for the site’s tile project.

“We’re running into quite a bit of problems out there due to soil and wetness,” District Administrator Andy Henschel said.

The tile allows the district to divert water around the cells ahead of the cell’s construction. He said the timing was urgent because the district needed to bid out the contract for the cells’ construction, which would take place after the tile was placed.